PMP Prep

Process — Scope, schedule, quality & procurement

Process · 41%Course 8/113 chapters

Operational module covering WBS/backlog, milestones, dependencies, critical path, quality, cost of quality, contracts, and vendor performance.

Estimated time : 100 min

Manage scopeManage scheduleOptimize qualityManage procurement

Learning objectives

  • Break scope into verifiable deliverables.
  • Read dependencies, float, and critical path.
  • Choose between prevention, assurance, control, and quality improvement.
  • Connect contract type, vendor risk, and procurement strategy.

Key concepts

WBS
Hierarchical decomposition of scope into deliverables and work packages.
PMBOK scope management
Critical path
Sequence of activities determining the minimum project duration; any slip delays the project.
PMBOK schedule management
Cost of quality
Cost of prevention and appraisal plus internal and external failure costs.
PMBOK quality management
Contract type
Financial risk allocation between buyer and seller: fixed price, time and material, cost reimbursable.
PMBOK procurement management

1. Scope: WBS, backlog, and acceptance

Scope is controlled only when everyone understands what is included, excluded, accepted, and measured. In predictive delivery, the WBS and baseline structure control; in agile, the prioritized backlog carries evolution.

ApproachScope artifactExpected control
PredictiveCharter, WBS, WBS dictionary, baselineImpact analysis + change control
AgileProduct backlog, user stories, acceptance criteriaValue prioritization + increment review
HybridBaseline for stable components + backlog for evolving componentsSeparate but integrated governance

Scope creep trap

An addition requested by a sponsor is still a change. Their authority does not remove impact analysis.

Artifact → decision → PMI action map

Artifact

Product backlog + Definition of Done + flow metrics

Decision

Does the work maximize value without breaking flow?

PMI action

Reprioritize with the PO, limit WIP, protect the sprint, and measure delivery.

Avoid: Adding work to the sprint or changing priority without value trade-off.

Recommendations

  • Always connect a deliverable to acceptance criteria.
  • Document exclusions to avoid misunderstandings.

Tips

  • Predictive = baseline; agile = backlog; hybrid = both with clear rules.
  • No hidden change in a governed project.

Chapter quiz

  1. 1.A sponsor asks to add a deliverable outside the baseline. What comes first?

2. Schedule: dependencies, float, and critical path

Schedule management depends on the approach: milestones and critical path in predictive, cadence and velocity in agile, dependency synchronization in hybrid.

Marge totale = LS - ES = LF - EF

If total float is 0, the activity is on the critical path.

StartEndA3jB5jC9jD2j
Critical path A-C-D = 14 d (red) > A-B-D = 10 d. Float of B = 4 d.

A CPM network shows why only some activities directly drive the final finish date.

Identifying the real impact of a delay

Two paths exist: A-B-D lasts 12 days and A-C-D lasts 14 days. Activity B slips by 2 days; activity C slips by 1 day.

  1. Initial critical path: A-C-D = 14 days because it is longer than A-B-D.
  2. After B slips: A-B-D = 14 days. The path reaches the critical path but does not exceed total duration yet.
  3. After C slips: A-C-D = 15 days. The project slips by 1 day.

The right action is to analyze the network before compressing: C directly threatens the finish date, while B consumes its float.

Classic responses to a delay

SituationHealthy response
Critical activity delayedAnalyze compression: fast tracking, crashing, risks, and cost.
Non-critical activity delayed within floatMonitor but do not panic.
Unstable external dependencyClarify commitment, risk, contingency plan, and communication.

Fast tracking vs crashing

Fast tracking: perform activities in parallel at the cost of increased risk. Crashing: add resources at the cost of increased cost.

Artifact → decision → PMI action map

Artifact

Cost/schedule baseline + EVM + vendor register

Decision

Is the variance cost, schedule, quality, or vendor-related?

PMI action

Calculate variance, forecast impact, propose correction, and update plans.

Avoid: Correcting the schedule without understanding the variance cause.

Recommendations

  • Analyze the critical path before compression.
  • Keep dependencies visible in the integrated plan.

Tips

  • Float 0 = maximum attention.
  • Compression = cost/risk trade-off, never automatic.

Chapter quiz

  1. 1.A non-critical activity has 5 days of float and slips by 2 days. What should you do?

3. Quality, procurement, and contracts

Quality and procurement meet in acceptance criteria: the project must define what will be accepted, how it will be verified, and how the vendor will be managed.

Cost of quality

CategoryExamplePMP reading
PreventionTraining, standards, test automationInvest early to avoid defects.
AppraisalReviews, audits, inspectionsVerify during the work.
Internal failureRework before deliveryVisible but recoverable cost.
External failureCustomer incident, warranty, reputationMost dangerous cost.

Contract types

ContractBuyer riskWhen to use
Fixed PriceLow if scope is clearStable and well-defined deliverable.
Time & MaterialMediumUncertain effort but need for flexibility.
Cost reimbursableHighResearch, innovation, high uncertainty.

Quality reflex

The PMP answer prefers preventing and improving the system rather than massively correcting at the end.

Artifact → decision → PMI action map

Artifact

Cost/schedule baseline + EVM + vendor register

Decision

Is the variance cost, schedule, quality, or vendor-related?

PMI action

Calculate variance, forecast impact, propose correction, and update plans.

Avoid: Correcting the schedule without understanding the variance cause.

Recommendations

  • Include quality criteria in vendor contracts.
  • Measure vendor performance regularly.
  • Address recurring defects through root cause.

Tips

  • Vague scope + fixed price = likely conflict.
  • Quality = conformance to requirements + fitness for use.

Chapter quiz

  1. 1.A vendor often delivers similar defects. Which action is most PMP-aligned?

Decision toolkit

PMP decision trees & running case

Use this when two answers look right: qualify the context, choose the artifact, then act.

Change request

A sponsor, customer, or user asks to change scope, cost, schedule, or quality.

  1. 1. Predictive approach with an approved baseline.

    Decision: Analyze impact before acting.

    Action: Document the request, assess impacts, then route it through integrated change control/CCB.

  2. 2. Agile approach with a product backlog.

    Decision: Do not disrupt the current sprint.

    Action: Add it to the backlog, clarify value, and reprioritize with the Product Owner.

  3. 3. Urgent compliance/safety-related change.

    Decision: Protect compliance and transparency.

    Action: Analyze quickly, inform governance authorities, and record the decision.

Trap: Implementing directly because the sponsor asked bypasses governance.

Risk vs issue

An event may happen or has just happened.

  1. 1. The event is uncertain.

    Decision: Treat it as a risk.

    Action: Qualify probability/impact, choose response, owner, and reserve.

  2. 2. The event has occurred.

    Decision: Treat it as an issue.

    Action: Create corrective action, assign an owner, and track to closure.

  3. 3. The issue creates new risks.

    Decision: Update both logs/registers.

    Action: Issue log for immediate action, risk register for remaining uncertainty.

Trap: A materialized risk is no longer just monitored: action is required.

Vendor delay

A vendor announces a delay, quality issue, or resource unavailability.

  1. 1. The contract defines SLAs, milestones, or penalties.

    Decision: Check commitments before negotiating.

    Action: Compare contract, actual performance, and project impacts.

  2. 2. The delay impacts the critical path or value.

    Decision: Evaluate alternatives and reserve.

    Action: Analyze fast tracking, replanning, another vendor, or scope trade-off.

  3. 3. The vendor relationship is recoverable.

    Decision: Collaborate without losing contractual control.

    Action: Dated action plan, checkpoints, and risk register update.

Trap: Threatening the vendor before analyzing contract and impact is a poor first response.

Digital project: omnichannel customer portal

Charter

Objective: reduce support calls by 25% in 6 months through secure self-service.

Backlog / WBS

Product backlog, MVP, monthly releases, Definition of Done including security and analytics.

Stakeholders

  • CX sponsor, Product Owner, dev team, security, support, pilot customers.
  • Success measured by adoption, resolution rate, and satisfaction.

Risks

  • Low adoption if the portal does not solve real pain points.
  • Security risk around authentication and personal data.

Change

Major change: add an AI chatbot. PMI response: value, risks, compliance, backlog, and prioritization.

EVM

Light EVM: release budget vs delivered value; also track burnup and real adoption.

Closure

Support transition, runbook, training, benefits measurement at 30/60/90 days.

Practical examples

Poorly framed fixed-price contract

Scenario : The customer wants fixed price while requirements change weekly.

Project manager's action : Clarify scope, change mechanism, or propose a more flexible contract.

Exam strategy

  • A scope change must be visible: WBS/baseline or backlog depending on approach.
  • On a delay, analyze critical path and dependencies before adding resources.
  • Quality is built early; final inspection is too late.
  • A vendor is managed through contract, acceptance criteria, performance, and relationship.

Module assessment

  1. 1.Which choice best reduces late defect risk?