PMP Prep
PMP formula desk

Exam-ready formulas

Review EVM, PERT, finance, risk and contract calculations with a fast, filterable decision-oriented layout.

26
formulas
26
abbreviations
6
families

Exam cues

A ratio > 1 is usually favorable for CPI, SPI and BCR.

A positive variance is good for SV, CV and VAC; a negative variance signals delay or overrun.

Every PMP formula you need, with its meaning, plus a dictionary of abbreviations.

AbAbbreviations dictionary

PV
Planned Value — budget of work planned
EV
Earned Value — budgeted value of work done
AC
Actual Cost — spent for the work done
BAC
Budget at Completion
SV
Schedule Variance
CV
Cost Variance
SPI
Schedule Performance Index
CPI
Cost Performance Index
EAC
Estimate at Completion
ETC
Estimate to Complete
VAC
Variance at Completion
TCPI
To-Complete Performance Index
O / M / P
Optimistic / Most likely / Pessimistic (three-point estimate)
tE
Expected duration (or cost)
σ
Standard deviation (sigma) — uncertainty measure
ES / EF
Early Start / Early Finish
LS / LF
Late Start / Late Finish
FV / PV
Future Value / Present Value (finance)
r / n
Discount rate / number of periods (or stakeholders)
NPV (VAN)
Net Present Value
IRR (TRI)
Internal Rate of Return
ROI
Return on Investment
BCR
Benefit-Cost Ratio
EMV
Expected Monetary Value
PTA
Point of Total Assumption — FPIF contract
PERT
Program Evaluation and Review Technique

Formulas

Earned value — measurement

5 formulas
  • Earned Value

    EV = BAC × % complete

    The budgeted value of the work actually done — the pivot of all EVM. It's "how much budget you have earned".

  • Schedule Variance

    SV = EV − PV

    Ahead or behind, expressed in money: have we earned as much value as planned by now?

    Positive = ahead; negative = behind.

  • Cost Variance

    CV = EV − AC

    Over- or under-cost in money: does the value earned cover what we spent?

    Positive = under budget; negative = over.

  • Schedule Performance Index

    SPI = EV / PV

    Schedule efficiency as a ratio: 0.90 means progressing at 90% of the planned pace.

    < 1 = behind; > 1 = ahead.

  • Cost Performance Index

    CPI = EV / AC

    Cost efficiency: 0.90 means you get $0.90 of value for every dollar spent.

    < 1 = over budget; > 1 = under budget.

Formulas

Earned value — forecasting

7 formulas
  • EAC (current rate)

    EAC = BAC / CPI

    The forecast total cost if the current cost performance (CPI) continues. The default exam formula.

  • EAC (one-off variance)

    EAC = AC + (BAC − EV)

    Final cost if the past variance was a one-off and the rest runs at the planned budget.

  • EAC (cost and schedule)

    EAC = AC + (BAC − EV) / (CPI × SPI)

    Final cost when both cost AND schedule will keep weighing on the remaining work.

  • Estimate to Complete

    ETC = EAC − AC

    What remains to spend to finish (forecast final cost − already spent).

  • Variance at Completion

    VAC = BAC − EAC

    The forecast final budget variance: will we end over or under the original budget?

    Negative = forecast overrun.

  • TCPI (to BAC)

    TCPI = (BAC − EV) / (BAC − AC)

    The efficiency you must hold on the REMAINING work to finish within the original budget.

    > 1 = must outperform the past (hard).

  • TCPI (to EAC)

    TCPI = (BAC − EV) / (EAC − AC)

    Same idea, but to hold the REVISED budget (EAC) instead of the original.

Formulas

Estimation & schedule

5 formulas
  • PERT (beta)

    tE = (O + 4M + P) / 6

    Expected duration (or cost) that heavily weights the most likely scenario (×4) to reduce bias.

    The ×4 always goes on M.

  • Triangular

    tE = (O + M + P) / 3

    Simple average of the three scenarios, unweighted.

  • Standard deviation

    σ = (P − O) / 6

    The estimate's uncertainty: ±1σ covers ≈ 68% of cases, ±3σ ≈ 99.7%.

    Uses only the extremes O and P.

  • Variance

    σ² = ((P − O) / 6)²

    The square of the standard deviation; variances add up along a path to estimate total uncertainty.

  • Total Float

    Float = LS − ES = LF − EF

    How long an activity can slip without delaying the project end.

    Zero on the critical path.

Formulas

Communication & risk

2 formulas
  • Communication channels

    n (n − 1) / 2

    The number of possible communication links; it grows with the square of the number of people (hence the complexity).

    n = stakeholders (including yourself).

  • Expected Monetary Value

    EMV = Probability × Impact

    A risk's average expected value; sum the EMVs to size the contingency reserve.

    Threat = negative; opportunity = positive.

Formulas

Finance & project selection

5 formulas
  • Present Value

    PV = FV / (1 + r)^n

    What a future amount is worth TODAY: future money is worth less (you discount it).

  • Net Present Value (NPV)

    NPV = Σ discounted cash flows − Investment

    The project's net value creation. NPV > 0 = worthwhile; among projects, pick the highest NPV.

  • Return on Investment

    ROI = (Net benefit / Cost) × 100

    Profitability as a percentage of the cost invested; prefer the highest ROI.

  • Benefit-Cost Ratio

    BCR = Benefits / Costs

    How much benefit per unit of cost; BCR > 1 = the project returns more than it costs.

    Highest is preferred.

  • Payback period

    Payback = Investment / annual cash flow

    The time to recover the initial investment; prefer the shortest payback.

Formulas

Procurement

2 formulas
  • Point of Total Assumption

    PTA = ((Ceiling − Target) / buyer share) + Target cost

    On an FPIF contract, the cost beyond which the SELLER bears 100% of the overrun (the buyer pays no more).

  • Margin (net value)

    Profit = Value − Cost

    The net value created: what the project returns once costs are subtracted.