Exam-ready formulas
Review EVM, PERT, finance, risk and contract calculations with a fast, filterable decision-oriented layout.
- 26
- formulas
- 26
- abbreviations
- 6
- families
Exam cues
A ratio > 1 is usually favorable for CPI, SPI and BCR.
A positive variance is good for SV, CV and VAC; a negative variance signals delay or overrun.
Every PMP formula you need, with its meaning, plus a dictionary of abbreviations.
AbAbbreviations dictionary
- PV
- Planned Value — budget of work planned
- EV
- Earned Value — budgeted value of work done
- AC
- Actual Cost — spent for the work done
- BAC
- Budget at Completion
- SV
- Schedule Variance
- CV
- Cost Variance
- SPI
- Schedule Performance Index
- CPI
- Cost Performance Index
- EAC
- Estimate at Completion
- ETC
- Estimate to Complete
- VAC
- Variance at Completion
- TCPI
- To-Complete Performance Index
- O / M / P
- Optimistic / Most likely / Pessimistic (three-point estimate)
- tE
- Expected duration (or cost)
- σ
- Standard deviation (sigma) — uncertainty measure
- ES / EF
- Early Start / Early Finish
- LS / LF
- Late Start / Late Finish
- FV / PV
- Future Value / Present Value (finance)
- r / n
- Discount rate / number of periods (or stakeholders)
- NPV (VAN)
- Net Present Value
- IRR (TRI)
- Internal Rate of Return
- ROI
- Return on Investment
- BCR
- Benefit-Cost Ratio
- EMV
- Expected Monetary Value
- PTA
- Point of Total Assumption — FPIF contract
- PERT
- Program Evaluation and Review Technique
Formulas
Earned value — measurement
Earned Value
EV = BAC × % completeThe budgeted value of the work actually done — the pivot of all EVM. It's "how much budget you have earned".
Schedule Variance
SV = EV − PVAhead or behind, expressed in money: have we earned as much value as planned by now?
Positive = ahead; negative = behind.
Cost Variance
CV = EV − ACOver- or under-cost in money: does the value earned cover what we spent?
Positive = under budget; negative = over.
Schedule Performance Index
SPI = EV / PVSchedule efficiency as a ratio: 0.90 means progressing at 90% of the planned pace.
< 1 = behind; > 1 = ahead.
Cost Performance Index
CPI = EV / ACCost efficiency: 0.90 means you get $0.90 of value for every dollar spent.
< 1 = over budget; > 1 = under budget.
Formulas
Earned value — forecasting
EAC (current rate)
EAC = BAC / CPIThe forecast total cost if the current cost performance (CPI) continues. The default exam formula.
EAC (one-off variance)
EAC = AC + (BAC − EV)Final cost if the past variance was a one-off and the rest runs at the planned budget.
EAC (cost and schedule)
EAC = AC + (BAC − EV) / (CPI × SPI)Final cost when both cost AND schedule will keep weighing on the remaining work.
Estimate to Complete
ETC = EAC − ACWhat remains to spend to finish (forecast final cost − already spent).
Variance at Completion
VAC = BAC − EACThe forecast final budget variance: will we end over or under the original budget?
Negative = forecast overrun.
TCPI (to BAC)
TCPI = (BAC − EV) / (BAC − AC)The efficiency you must hold on the REMAINING work to finish within the original budget.
> 1 = must outperform the past (hard).
TCPI (to EAC)
TCPI = (BAC − EV) / (EAC − AC)Same idea, but to hold the REVISED budget (EAC) instead of the original.
Formulas
Estimation & schedule
PERT (beta)
tE = (O + 4M + P) / 6Expected duration (or cost) that heavily weights the most likely scenario (×4) to reduce bias.
The ×4 always goes on M.
Triangular
tE = (O + M + P) / 3Simple average of the three scenarios, unweighted.
Standard deviation
σ = (P − O) / 6The estimate's uncertainty: ±1σ covers ≈ 68% of cases, ±3σ ≈ 99.7%.
Uses only the extremes O and P.
Variance
σ² = ((P − O) / 6)²The square of the standard deviation; variances add up along a path to estimate total uncertainty.
Total Float
Float = LS − ES = LF − EFHow long an activity can slip without delaying the project end.
Zero on the critical path.
Formulas
Communication & risk
Communication channels
n (n − 1) / 2The number of possible communication links; it grows with the square of the number of people (hence the complexity).
n = stakeholders (including yourself).
Expected Monetary Value
EMV = Probability × ImpactA risk's average expected value; sum the EMVs to size the contingency reserve.
Threat = negative; opportunity = positive.
Formulas
Finance & project selection
Present Value
PV = FV / (1 + r)^nWhat a future amount is worth TODAY: future money is worth less (you discount it).
Net Present Value (NPV)
NPV = Σ discounted cash flows − InvestmentThe project's net value creation. NPV > 0 = worthwhile; among projects, pick the highest NPV.
Return on Investment
ROI = (Net benefit / Cost) × 100Profitability as a percentage of the cost invested; prefer the highest ROI.
Benefit-Cost Ratio
BCR = Benefits / CostsHow much benefit per unit of cost; BCR > 1 = the project returns more than it costs.
Highest is preferred.
Payback period
Payback = Investment / annual cash flowThe time to recover the initial investment; prefer the shortest payback.
Formulas
Procurement
Point of Total Assumption
PTA = ((Ceiling − Target) / buyer share) + Target costOn an FPIF contract, the cost beyond which the SELLER bears 100% of the overrun (the buyer pays no more).
Margin (net value)
Profit = Value − CostThe net value created: what the project returns once costs are subtracted.